§ 244-36. Inspection requirements.
| |||||||
A. Inspection, testing and engineering administration fees. Prior to the signing of any final plat, issuance of a development permit or the start of construction of any improvements required by the provisions of this chapter, the developer shall deposit, by cash or certified check, with the Planning and Zoning Office an amount determined from the appropriate schedule under this chapter. Said amount shall be used to defray the cost of inspection, testing, engineering, administration and other costs and fees paid by the Township in connection with the inspection and acceptance of the installation of the required improvements.
| |||||||
B. Inspection notice. All required improvements, except those utility improvements which are not the responsibility of the Township, shall be subject to inspection and approval by the Township Engineer, who shall be notified by the developer at least five days prior to the initial start of construction and again 48 hours prior to the resumption of work after any idle period exceeding one working day. All of the utility improvements shall be subject to inspection and approval by the owner of or agency controlling the utility, who shall be notified by the developer in accordance with the utilities requirements. No underground installation shall be covered until it is inspected and approved by the owner of or agency controlling the utility or by the Township Engineer in all other cases.
| |||||||
C. Modification of improvements. At any time, whether as a result of his inspection of work underway or otherwise, the Township Engineer may recommend that the developer be required to modify the design and extent of the improvements required, notifying the Planning Board of his recommendations. The Planning Board shall, if it considers such modifications to be major or if requested by the developer or Township Engineer, take formal action to approve or disapprove such recommendations; provided, however, that it must first afford the developer an opportunity to be heard. If the Board takes no formal action within 30 days of such recommendations or where the developer has not requested formal Planning Board action, its approval will be assumed. Similarly, the Planning Board may grant or deny the developer permission to effect such modification upon his application and the Township Engineer's approval. In either event, where such modification is to be effected, the appropriate plat must be revised by the developer or his engineer to reflect such modification and sufficient copies thereof submitted to the administrative officer for distribution.
| |||||||
D. General inspection requirements. All improvements, except as otherwise provided, shall be subject to inspection and approval by the Township Engineer. No underground installation shall be covered until inspected and approved by the Township Engineer or those agencies having jurisdiction over the particular installation. If such installation is covered prior to inspection, it shall be uncovered or other inspection means used, such as a television or other pipeline camera, as may be deemed necessary by the Township Engineer, and charges for such work will be paid for by the developer.
| |||||||
E. Inspection not acceptance. Inspection of any work by the Township Engineer or his authorized representative shall not be considered to be final approval or rejection of the work but shall only be considered to be a determination of whether or not the specific work involved was being done to Township specifications or other required standards at the time of inspection. Any damage to such work or other unforeseen circumstances, such as the effect of the weather, other construction, changing conditions, settlement, etc., between the time of installation and the time that the developer wishes to be released from his performance guaranty shall be the full responsibility of the developer, and no work shall be considered accepted until release of the performance guaranty.
| |||||||
F. Procedure on acceptance of public improvements. When the developer has constructed and installed the streets, drainage facilities, curbs, sidewalks, street signs, monuments and other improvements in accordance with Township regulations, standards and specifications and desires the Township to accept said improvements, he shall, in writing, addressed to and in a form approved by the Township Committee, with copies thereof to the Township Engineer, request the Township Engineer to make a semifinal inspection of said improvements. If the improvements have been constructed under a performance guaranty after approval of a final plat, the developer shall submit an as-built plan showing as-built grades, profiles and sections and locations of all subsurface utilities, such as French drains, combination drains, sanitary sewage disposal systems, both public and individual waterlines and control valves, gas lines, telephone conduits, monuments, iron property markers and any other utilities or improvements installed other than as shown on the approved final plat. Said as-built plan shall be certified to by a licensed New Jersey professional engineer. If any improvements are constructed prior to final plat approval, the final plat shall reflect all changes and as-built conditions and be so certified. Said as-built plan(s) shall be submitted on reproducible media.
| |||||||
§ 244-37. Site maintenance during construction.
| |||||||
A. It shall be the responsibility of the developer to maintain the entire site or subdivision in a safe and orderly condition during construction. Necessary steps shall be taken by the developer to protect occupants of the site or subdivision and the general public from hazardous and unsightly conditions during the entire construction period. These steps shall include but are not limited to the following:
| |||||||
(1) Open excavations shall be enclosed by fencing or barricades during nonconstruction hours. Movable barricades shall be equipped with yellow flashing hazard markers or other lighting during the hours or darkness.
| |||||||
(2) The excavation of previously installed sidewalk and pavement areas which provide access to occupied buildings in the site or subdivision shall be clearly marked with signs and barricades. Alternate safe access shall be provided for pedestrians and vehicles to the occupied buildings.
| |||||||
(3) Materials stored on the site shall be screened from the view of occupants of the subdivision or site and adjoining streets and properties.
| |||||||
(4) Construction equipment, materials and trucks shall not be stored within 150 feet of occupied buildings in the site or subdivision and adjoining streets and properties during nonconstruction hours.
| |||||||
(5) Safe vehicular and pedestrian access to occupied buildings in the site or subdivision shall be provided at all times.
| |||||||