ARTICLE XI Site Plan Requirements
|
§225-77. Submission and approval required ; exceptions. [Amended 2-22 -1984 by Ord. No.3-1984]
|
|
A. Except as hereinafter provided, no building permit shall be issued for a building or change of use or enlargement of any building or use unless a site plan is first submitted and approved in accordance with the Land Development Ordinance and no certificate of occupancy shall be given unless all construction conforms to the approved plan.
|
|
B. Temporary certificates of occupancy.
|
| |
(1) The Planning Board may authorize the issuance of temporary certificates of occupancy for good cause shown, and, furthermore, the Chief Construction Official shall be authorized to issue a temporary certificate of occupancy for any nonresidential development for a period of time not to exceed 180 days. Temporary certificates of occupancy shall be issued only for the following exterior site improvements:
|
| | |
(a) Landscaping and seeding.
|
| | |
(b) Final paving surface.
|
| | |
(c) Freestanding sign(s).
|
| |
(2) The time period of a temporary certificate of occupancy issued by the Chief Construction Official shall be extended only by an action of the Planning Board of Egg Harbor Township.
|
|
C. All volunteer fire companies and ambulance and rescue squads of the Township of Egg Harbor shall not have to satisfy site plan requirements.
|
|
[Added 10-8-1986 by Ord. No. 39-1986]
|
|