(2) For purposes of TSS reduction calculations, Table 2 below presents the presumed removal rates for certain BMPs designed in accordance with the New Jersey Stormwater Best Management Practices Manual. The BMP Manual may be obtained from the address identified in | |||||||
(3) If more than one BMP in series is necessary to achieve the required eighty-percent TSS reduction for a site, the applicant shall utilize the following formula to calculate TSS reduction:
| |||||||
R = AB-(AXB)/100 Where | |||||||
R -- total TSS percent load removal from application of both BMPs | |||||||
A = the TSS percent removal rate applicable to the first BMP | |||||||
B -- the TSS percent removal rate applicable to the second BMP | |||||||